EXPERIENCE BUILT BY THE BILLIONS

Geocomposite Liner Install for an Energy Waste Landfill in New Mexico

Mustang Extreme Environmental Services installs landfills for all uses across the country. This is an example of a project in the Delaware Basin of NM where we are installing just under 3 million sq ft of geocomposite liner for an Energy Waste Landfill.

Dual, Million-barrel Produced Water Pond Installation in the Permian Basin

We are proud to share details of a best-in-class turnkey installation of dual, million-barrel produced water ponds in the Permian Basin. What sets Mustang Extreme Environmental Services apart? Stellar craftsmanship by our experienced crew with exceptional project management. Intensive QAQC inspection by our highly trained specialists. The Mustang Extreme proprietary M.E.G.A. Remote Leak Detention and

Fast-Deploy Cl02 Mobile Unit Restores AST Water in Just Four Days

Solving complex and difficult water quality issues is one of our specialties. For an operator in Howard County, TX, extremely high bacteria levels and solids made water stored in an AST unusable for frac. Unsuccessful attempts to clean the water left the operator few options. Frustrated and in need of a remedy, they contacted the

Composite Mats with Geotextile Fabric Underlayment Used to Create Compliant Frac Pad in Pennsylvania

A great example of a compliant frac pad drill site in Pennsylvania. Mustang Extreme Environmental Services installed interlocking composite mats with a geotextile fabric underlayment to ensure containment of an upright tank farm. The extrusion welding shows off our expert craftsmanship.

Iron Sulfide Buildup in Injection Well Piping Treated in Two Days Using Cl02

Iron sulfide buildup in injection well piping caused critical delays at a main centralized oil and gas gathering facility in the Delaware Basin. Using the Mustang Aria 5 Cl02 mobile unit, Mustang Extreme Environmental Services water treatment specialists successfully cleaned out the pipe in just 2 days, allowing normal frac operations to resume. Having issues

Refinery Retention Pond Installation in Tulsa, Oklahoma

Mustang Extreme Environmental Services recently completed a Tulsa Refinery Retention Pond.

Composite Matting Installation for Precision Drill Rig Platform at Cornell University

Dual Pond Installation for Commercial Re-Use in the Powder Basin of Wyoming

Environmental Liner Installed to Create Freshwater Pond in Encinal, Texas

Geosynthetic Liner and Manifold System Installation in the Eagle Ford Basin

Need Help? Contact Us About Your Next Project