Iron Sulfide Buildup in Injection Well Piping Treated in Two Days Using Cl02
Iron sulfide buildup in injection well piping caused critical delays at a main centralized oil and gas gathering facility in the Delaware Basin.
Using the Mustang Aria 5 Cl02 mobile unit, Mustang Extreme Environmental Services water treatment specialists successfully cleaned out the pipe in just 2 days, allowing normal frac operations to resume.